Your customer runs two daily shifts in their plant: morning shift and evening shift. A resource, LATHE, is assigned to the work center W1. There are five units of LATHE available, of which three units are available for the morning shift and the remaining units for the evening shift.
Which two actions must the customer perform to associate LATHE with W1?
To allocate specific units of the LATHE resource to morning and evening shifts in Oracle Manufacturing Cloud, you need to configure the resource availability per shift as follows:
Deselect the Available 24 Hours check box -- This ensures that the resource availability is limited to specific shifts instead of being available 24/7.
Enter 3 in the Morning Shift column -- Assigning 3 units of LATHE to the morning shift allocates those units for use only during the morning.
Enter 2 in the Evening Shift column -- Assigning 2 units to the evening shift ensures that the remaining LATHE units are available for the evening shift.
Clarinda
2 months agoSalome
23 days agoKatheryn
25 days agoGalen
1 months agoCarman
2 months agoShonda
2 months agoAshlyn
1 months agoDalene
2 months agoVincent
2 months agoHelaine
2 months agoKeneth
2 months agoHelaine
2 months agoFabiola
3 months agoNobuko
2 months agoCasie
2 months agoDottie
2 months agoVincenza
2 months ago