Oracle Exam 1z0-466 Topic 2 Question 1 Discussion

Actual exam question for Oracle's 1z0-466 exam
Question #: 1
Topic #: 2
[All 1z0-466 Questions]

Which three statements are true about the Validated Scope of the project?

Show Suggested Answer Hide Answer
Suggested Answer: B, D, E

B: Scope Management - The goal of the Scope Management process is to identify clear boundaries of what is to be implemented and what key work products are to be produced.

D: A work breakdown structure permits summing of subordinate costs for tasks, materials, etc., into their successively higher level ''parent'' tasks, materials, etc. For each element of the work breakdown structure, a description of the task to be performed is generated. This technique (sometimes called a system breakdown structure) is used to define and organize the total scope of a project.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77