A one-time additional public holiday has been announced for this year. You update the PA Calendar, which is used for Resourcing with this exception. Select the two options required to ensure that this change is reflected in the existing assignment on resource calendars.
Changes to these calendars impact the schedules of the person resources, requirements, and assignments differently. Oracle Project Resource Management provides the following administrative processes to help manage these changes and to maintain consistent schedule information throughout the application:
PRC: Generate Calendar Schedule for a Single Calendar
PRC: Generate Calendar Schedules for a Range of Calendars
PRC: Rebuild Timeline for a Single Resource
PRC: Rebuild Timeline for a Range of Resources