A project is enabled for Burdening by setting up a burden schedule at the project type level. A Miscellaneous expenditure Item Is charged to the project with a raw cost of $100 and expenditure type "Overhead." The "Overheads" expenditure type is excluded from all cost bases in the burden structure. What happens when the "PRC: Distribute usage and Miscellaneous Costs" program is run for this project?
Note:
* Distribute Usage and Miscellaneous Costs
The process computes the costs and determines the default GL account to which to post the cost for expenditure items with the following expenditure type classes:
Usages
Burden Transactions
Miscellaneous Transactions
Inventory and WIP transactions not already costed or accounted