Oracle Exam 1Z0-567 Topic 7 Question 6 Discussion

Actual exam question for Oracle's 1Z0-567 exam
Question #: 6
Topic #: 7
[All 1Z0-567 Questions]

Identify the true statement regarding Schedule Checker.

Show Suggested Answer Hide Answer
Suggested Answer: B, C, D

Note: The new schedule checker is a tool that assists planners, project managers and the PMO to ensure project plans are built within the guidelines of industry and organizational best practices. The schedule checker performs a 14-point analysis to ensure that activities and dependencies of the project schedule are following desired standards. The schedule checker adheres to the DCMA 14-point assessment check and produces a report that lists all opportunities for corrective action or improvement when aspects of the project schedule fall outside the quality guidelines. The report includes a summary and detailed sections displaying activities falling outside your configured thresholds.

Note 2: The Schedule Checker can be run against one or multiple projects. You can save the thresholds to run again for the project that is open.

The first thing to do is set up the 14 Configurable User Thresholds. See figure below.

Example of output.

Shown below is the top half of the Schedule Check Summary Report.

Reference below the lower half of the Schedule Check report.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77