You created a sourcing two-stage sealed RFQ and invited five suppliers to participate. The Technical stage is completed and the Commercial stage is unlocked.
At this time in the award negotiation section, in the Award Line you are able to see only three supplier's responses as active responses. You are not able to see the other two suppliers' data in the active responses.
Which two reasons are causing this?
C: If you are not able to submit a response to an initiative, you can request that the category manager submit a surrogate
response on your behalf.
E: You can specify a minimum score value that all responses must meet or surpass for that response to be shortlisted for
awarding. When you begin awarding the negotiation, you apply the knockout score. All responses having a requirement
response value that doesn't meet the knock out value are marked as not shortlisted for awarding.