TIX provides services to the informatic equipment of large organisations. They operate an ISO 9001:2015 QMS that is being audited by an important
customer (second-party audit). During the audit, the audit team has identified two nonconformities. When preparing the Closing meeting, the audit
team discussed and agreed both nonconformities with TIX's quality manager. The Closing meeting was planned for 6pm with the general manager,
quality manager and service manager at the meeting room.
At 6pm, when the audit team enters the meeting room, only two people are present and waiting for them: the Health and Safety supervisor and the
warehouse supervisor. Neither have participated in the audit.
The dialogue among them is as follows:
Audit team leader: "Good evening, could you please inform the three managers that we are ready to start with the Closing meeting?"
Health and Safety supervisor: "Good evening. We are sorry to inform you that the general manager was involved in a serious car accident, and
the other two managers have had to leave urgently to attend the emergency."
Warehouse supervisor: "They have asked us to listen to what you need to say and to sign whatever we need to sign. We also have a message
from them about the two nonconformities. They wanted us to ask you if you could contact them in a couple of days to determine how to proceed."
Which one of the following options would be your preferred response to the final comment made by the warehouse manager?
Tegan
7 months agoRhea
7 months agoMaybelle
7 months agoRhea
7 months agoLachelle
6 months agoIvette
7 months agoMarla
7 months agoEric
8 months agoSylvie
8 months agoGolda
8 months ago