PeopleCert Exam 18 Topic 2 Question 24 Discussion

Actual exam question for PeopleCert's IASSC Lean Six Sigma - Yellow Belt exam
Question #: 24
Topic #: 2
[All IASSC Lean Six Sigma - Yellow Belt Questions]

Training cost $2,500 and a project required an initial investment of $23,500. If the project yields monthly savings of $2,500 beginning after 4 months, what is the payback period in months (before money costs and taxes)?

Show Suggested Answer Hide Answer
Suggested Answer: C