Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PeopleCert Exam PRINCE2 Agile Practitioner Topic 5 Question 6 Discussion

Actual exam question for PeopleCert's PRINCE2 Agile Practitioner exam
Question #: 6
Topic #: 5
[All PRINCE2 Agile Practitioner Questions]

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information

A new website will be built for the event. There are five work packages within this product:

1. Initial homepage:

2. Team Registration functionality:

3. Social media promoting the event and its aims.

4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.

5. Health Park:

The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.

The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.

Using the Project Scenario and Website Additional information, answer the following question:

The Apps and Social Media work package includes the following requirements:

1. Fitness app - Must Have

2. Healthy eating app - Should Have

The burn-down chart is showing an ever-increasing negative gap between the ideal rate of progress and what has actually been delivered. The team manager decided not to deliver the healthy eating app. However, it is still forecast that requirement 1 cannot be completed within the current timebox.

The team manager escalated the issue to the project manager who instructed the team manager to immediately remove the burn-down chart from the information radiator.

What BEST explains how this approach applies the 'manage by exception' principle while taking into account the PRINCE2 Agile behaviours?

Show Suggested Answer Hide Answer
Suggested Answer: C

By removing the burn-down chart from the information radiator, the project manager limits the team's ability to visualize and manage their progress and challenges. In PRINCE2 Agile, teams should be empowered to handle issues within their work package, and transparency through tools like the burn-down chart is essential for self-management and collaboration.


Contribute your Thoughts:

Kenneth
2 days ago
Hah, 'Mission Control' - the project manager's clearly going for a NASA vibe here. Let's hope the team doesn't have to do any space walks to deliver this project!
upvoted 0 times
...
Soledad
3 days ago
I don't know, the team manager did escalate the issue to the project manager, so it's not like they were just ignoring it. I guess the project manager wanted to take control of the situation.
upvoted 0 times
...
Mireya
7 days ago
Yes, it's important for the project manager to step in when needed to ensure the project stays on track.
upvoted 0 times
...
Troy
10 days ago
I agree, it shows that the project manager is taking control and managing the situation.
upvoted 0 times
...
Elke
14 days ago
I think the project manager made the right call by removing the burn-down chart.
upvoted 0 times
...
Vesta
19 days ago
The project manager's decision to remove the burn-down chart seems a bit heavy-handed. The team should be empowered to deal with issues within their work package, not shut down the transparency of the process.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77