PMI Exam PgMP Topic 1 Question 79 Discussion

Actual exam question for PMI's PgMP exam
Question #: 79
Topic #: 1
[All PgMP Questions]

A biometrics firm has a facial recognition program with multiple components and project managers. The

project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of impact and probability of occurring.

What should the program manager do first?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Alberta
5 months ago
C is the way to go. Documenting the risk is the first step, and it's better than just throwing money at the problem.
upvoted 0 times
Nelida
4 months ago
Agreed, documenting the risk is important before taking any further action.
upvoted 0 times
...
Nydia
4 months ago
I think we should add the risk details to the program risk register.
upvoted 0 times
...
...
Barabara
6 months ago
I'll have to go with C. Putting the risk details in the register is the smart move, and it's probably the least amount of work too.
upvoted 0 times
...
Valentin
6 months ago
B seems like the logical choice. Communicating the risk to all project managers will help them manage it at the component level.
upvoted 0 times
Rutha
5 months ago
It's important to keep everyone informed and involved in managing the risk.
upvoted 0 times
...
Jettie
5 months ago
Agreed, that way they can manage it at the component level.
upvoted 0 times
...
Sherman
5 months ago
I think we should communicate the risk to all project managers.
upvoted 0 times
...
...
Suzan
6 months ago
I agree with Nikita. It's important to document the risk analysis for future reference.
upvoted 0 times
...
Lucille
6 months ago
D is the way to go. Collaborating with the project manager to develop a response is crucial in this situation.
upvoted 0 times
Daniela
6 months ago
Working together to develop a response will help mitigate the impact of the risk.
upvoted 0 times
...
Benton
6 months ago
I think it's important to have a detailed risk response plan in place.
upvoted 0 times
...
France
6 months ago
Agreed, collaborating with the project manager is key in addressing the risk.
upvoted 0 times
...
...
Nikita
6 months ago
I think the program manager should add the risk details to the program risk register.
upvoted 0 times
...
Portia
6 months ago
I think C is the correct answer. Documenting the risk in the program risk register is the first step before taking any other action.
upvoted 0 times
Kenneth
5 months ago
Yes, it's essential to have all risks documented in one central location for better visibility and control.
upvoted 0 times
...
Kyoko
5 months ago
I agree, documenting the risk in the program risk register is important for tracking and managing.
upvoted 0 times
...
Johana
5 months ago
Yes, it's important to have a centralized place where all risks are recorded and analyzed.
upvoted 0 times
...
Gracia
6 months ago
Once it's in the risk register, we can then decide on the best course of action to address it.
upvoted 0 times
...
Donette
6 months ago
I agree, documenting the risk in the program risk register is crucial for tracking and managing it.
upvoted 0 times
...
Lemuel
6 months ago
I agree, documenting the risk in the program risk register is crucial for tracking and managing it.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77