PMI Exam PgMP Topic 2 Question 31 Discussion

Actual exam question for PMI's PgMP exam
Question #: 31
Topic #: 2
[All PgMP Questions]

A program manager is appointed to manage a new program. The organization's leadership has specified a list of benefits that the program should deliver and has requested that the program manager determine when incremental benefits can be realized.

What should the program manager do first?

Show Suggested Answer Hide Answer
Suggested Answer: A