Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 2 Question 77 Discussion

Actual exam question for PMI's PgMP exam
Question #: 77
Topic #: 2
[All PgMP Questions]

The risk manager completes risk response planning. The risk manager believes that to effectively address all eventualities, an additional action is required.

What should the program manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Sena
6 months ago
True, a contingency reserve is more comprehensive. Finalizing with B.
upvoted 0 times
...
Karima
6 months ago
Could be, but avoiding threats doesn’t always account for unforeseen problems.
upvoted 0 times
...
Oren
6 months ago
But shouldn’t we avoid known critical project threats first? Option C?
upvoted 0 times
...
Horace
7 months ago
Yeah, a contingency reserve can cover unexpected issues. Sounds logical.
upvoted 0 times
...
Sena
7 months ago
I think establishing a contingency reserve makes sense, so option B.
upvoted 0 times
...
Karima
7 months ago
Interesting question. What should the program manager do next?
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77