Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 3 Question 66 Discussion

Actual exam question for PMI's PgMP exam
Question #: 66
Topic #: 3
[All PgMP Questions]

The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan, determines that project A can wait until the resource becomes available, and assigns the resource to project B.

This is an example of which of the following?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Werner
8 months ago
But wait, isn't program resource management planning a valid option too? The program manager is reviewing the plan and making a decision based on that.
upvoted 0 times
...
Melina
8 months ago
Hmm, I'm leaning towards option C. Seems like the program manager is managing the interdependency between the two projects and the shared resource.
upvoted 0 times
...
Leana
8 months ago
No kidding! Alright, let's break this down. The key seems to be that the program manager is making a decision to prioritize one project over the other based on the resource availability.
upvoted 0 times
...
Tiffiny
8 months ago
Haha, yeah, this is getting complicated. I feel like I need a flow chart to keep track of all the moving parts here.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77