You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent
$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind
schedule. Based on this information, what is the schedule performance index (SPI) for this program?
Kimbery
1 months agoLizbeth
1 months agoTyra
17 days agoElza
19 days agoBea
1 months agoMuriel
2 months agoCathrine
9 days agoLeslee
10 days agoDarrin
17 days agoMelynda
1 months agoTwana
2 months agoDelfina
2 months agoLauran
2 months agoTalia
2 months agoDorsey
15 days agoFrank
19 days agoBritt
2 months agoShala
2 months agoMitsue
2 months agoReita
3 months agoVincent
3 months ago