PMI Exam PgMP Topic 5 Question 37 Discussion

Actual exam question for PMI's PgMP exam
Question #: 37
Topic #: 5
[All PgMP Questions]

A program to implement a company's new system is nearing completion and the program manager attempts to close the program. However, despite training provided to the operational staff on the new system, there is concern that the defined expected benefits will not be fully realized.

To prevent this concern in the future, which of the following should occur?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!