PMI Exam PgMP Topic 5 Question 81 Discussion

Actual exam question for PMI's PgMP exam
Question #: 81
Topic #: 5
[All PgMP Questions]

One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set.

If the tolerance range is too narrow on a program, what effect will multiple minor changes have on the program?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Kimberlie
4 months ago
Hmm, I'd say D) Slow down in program implementation. With a narrow tolerance range, every hiccup turns into a crisis. This program is like a car with square wheels - it's gonna be a bumpy ride!
upvoted 0 times
Lindy
4 months ago
Yeah, B) Degradation of program communications could definitely happen too. With so many changes happening, it's important to make sure everyone is on the same page.
upvoted 0 times
...
Cecilia
4 months ago
I think A) Reduction in program quality could also be a consequence. When you're constantly making minor changes, it's easy for things to slip through the cracks.
upvoted 0 times
...
Eliz
4 months ago
I agree, D) Slow down in program implementation seems likely. It's hard to keep things moving smoothly when there's no room for flexibility.
upvoted 0 times
...
...
Markus
4 months ago
B) Degradation of program communications. Oof, that's a tough one. When changes are a constant battle, communication breaks down faster than a cheap microwave. This program is like a game of telephone gone wrong.
upvoted 0 times
Marva
3 months ago
D) Slow down in program implementation
upvoted 0 times
...
Dawne
3 months ago
C) Reduction in program risk
upvoted 0 times
...
Janine
3 months ago
B) Degradation of program communications
upvoted 0 times
...
Monroe
4 months ago
A) Reduction in program quality
upvoted 0 times
...
...
Colby
5 months ago
That's a good point, Otis. However, I still think the main impact would be a slow down in program implementation.
upvoted 0 times
...
Otis
5 months ago
But wouldn't it also reduce program risk by catching issues early on?
upvoted 0 times
...
Tequila
5 months ago
I agree with Veronica, having a narrow tolerance range can definitely slow things down.
upvoted 0 times
...
Xochitl
5 months ago
A) Reduction in program quality. Totally agree. With a tight tolerance range, there's no room for adjustments, and quality is bound to suffer. This program is like a delicate flower that can't handle a little pruning.
upvoted 0 times
Olive
4 months ago
C) Reduction in program risk. I believe that with a narrow tolerance range, the program becomes more susceptible to risks as there's less room for error.
upvoted 0 times
...
Lorrine
4 months ago
D) Slow down in program implementation. Multiple minor changes could slow down the progress of the program if there's not enough room for adjustments.
upvoted 0 times
...
Rachael
4 months ago
A) Reduction in program quality. I agree, quality will definitely be impacted if there's not enough flexibility in the tolerance range.
upvoted 0 times
...
Alica
4 months ago
B) Degradation of program communications. I think constant minor changes could lead to confusion and miscommunication among team members.
upvoted 0 times
...
...
Belen
5 months ago
D) Slow down in program implementation. Definitely! A narrow tolerance range means even minor changes can cause major disruptions and delays. The program will be like a turtle trying to run a marathon.
upvoted 0 times
Cristal
4 months ago
B) Degradation of program communications
upvoted 0 times
...
Cheryl
4 months ago
D) Slow down in program implementation. Absolutely, even small changes can have a big impact on the program timeline.
upvoted 0 times
...
Terrilyn
4 months ago
A) Reduction in program quality
upvoted 0 times
...
...
Veronica
6 months ago
I think if the tolerance range is too narrow, multiple minor changes will slow down program implementation.
upvoted 0 times
...

Save Cancel