PMI Exam PMI-100 Topic 1 Question 38 Discussion

Actual exam question for PMI's PMI-100 exam
Question #: 38
Topic #: 1
[All PMI-100 Questions]

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!