Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-100 Topic 2 Question 79 Discussion

Actual exam question for PMI's PMI-100 exam
Question #: 79
Topic #: 2
[All PMI-100 Questions]

When cost variance is negative and schedule variance is positive, the project is:

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Daryl
3 months ago
I think the correct answer is A, because being under budget is a bigger concern than being behind schedule.
upvoted 0 times
...
Tonette
3 months ago
But positive schedule variance means we are ahead of schedule, so it's a bit confusing.
upvoted 0 times
...
Helga
3 months ago
I agree with Angelyn, negative cost variance means we are spending less than planned.
upvoted 0 times
...
Angelyn
3 months ago
A) under budget and behind schedule.
upvoted 0 times
...
Tomas
3 months ago
I think the correct answer is A, because being under budget is a bigger concern than being behind schedule.
upvoted 0 times
...
Shenika
4 months ago
This question is like a bad dad joke. 'When cost variance is negative and schedule variance is positive, the project is... behind schedule and over budget, of course!' *chuckles*
upvoted 0 times
Rebecka
3 months ago
D) complete; all planned values have been earned.
upvoted 0 times
...
Lucy
3 months ago
C) on schedule.
upvoted 0 times
...
Ethan
3 months ago
B) over budget and ahead of schedule.
upvoted 0 times
...
Micah
3 months ago
A) under budget and behind schedule.
upvoted 0 times
...
...
Lachelle
4 months ago
But positive schedule variance means we are ahead of schedule, so it's a bit confusing.
upvoted 0 times
...
Hector
4 months ago
I agree with Wai, negative cost variance means we are spending less than planned.
upvoted 0 times
...
Ardella
4 months ago
Complete? All planned values earned? No way, this project sounds like a hot mess. I'm going with B, the only logical answer here.
upvoted 0 times
Olga
3 months ago
Yeah, definitely over budget but at least ahead of schedule.
upvoted 0 times
...
Cecilia
3 months ago
I agree, B seems like the most logical choice in this situation.
upvoted 0 times
...
...
Georgeanna
4 months ago
Wait, how can the project be on schedule if the cost is negative and the schedule is positive? That doesn't make sense. I'll go with A.
upvoted 0 times
...
Whitley
4 months ago
Aha! I got this one. When you're over budget but ahead of schedule, that's exactly what option B describes. Easy peasy.
upvoted 0 times
Sunshine
3 months ago
A: Yup, that's correct. It's important to keep an eye on both cost and schedule variances.
upvoted 0 times
...
Emmanuel
3 months ago
B: So, the project is progressing faster than planned but costing more than expected.
upvoted 0 times
...
Bev
4 months ago
A: B) over budget and ahead of schedule.
upvoted 0 times
...
...
Wai
4 months ago
A) under budget and behind schedule.
upvoted 0 times
...
Rebbecca
4 months ago
Hmm, this one's tricky. If the cost is under budget but the schedule is behind, that doesn't sound too good. I'm thinking B is the way to go.
upvoted 0 times
Carri
4 months ago
Exactly, it's important to keep track of both cost and schedule variances.
upvoted 0 times
...
Frank
4 months ago
So, it means the project is not going as planned.
upvoted 0 times
...
Trevor
4 months ago
Yeah, if the cost is over budget but the schedule is ahead, that makes sense.
upvoted 0 times
...
Leontine
4 months ago
I think B is correct too.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77