PMI Exam PMI-ACP Topic 1 Question 69 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 69
Topic #: 1
[All PMI-ACP Questions]

During a retrospective meeting, a team develops a large list of initiatives All will have a positive impact and improve team performance What should the agile coach do next?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Carissa
8 months ago
Ha, implementing the most complex initiative? What is this, a test of endurance? I'd steer clear of that one.
upvoted 0 times
...
Kallie
8 months ago
Definitely, the coach needs to guide the team and not just let them run wild with all these ideas. Gotta start small and iterate.
upvoted 0 times
...
Ceola
8 months ago
Agreed, Rosenda. Positive progress is key, not just a long list of good intentions. The coach has to be strategic here.
upvoted 0 times
Adaline
8 months ago
C) Help the team choose one or two initiatives for immediate implementation.
upvoted 0 times
...
Renato
8 months ago
A) Positively acknowledge the list and share it with management
upvoted 0 times
...
Luz
8 months ago
C) Help the team choose one or two initiatives for immediate implementation.
upvoted 0 times
...
Kenia
8 months ago
During a retrospective meeting, a team develops a large list of initiatives. All will have a positive impact and improve team performance. What should the agile coach do next?
upvoted 0 times
...
...
Rosenda
8 months ago
I think C is the way to go - help the team choose one or two high-impact initiatives and get them implemented quickly. Build that momentum!
upvoted 0 times
...