Question #: 35
Topic #: 7
[All PMI-ACP Questions]

A project is starling and the type of wont is complex and suitable for agile in assessing the learn members it appears that co-location would be a challenge.

What should the agile practitioner do?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!