Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 10 Question 93 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 93
Topic #: 10
[All PMI-RMP Questions]

A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Dierdre
3 days ago
A) Create a new project plan including the new risks. Sounds like a good idea to me. Gotta stay on top of those curveballs, am I right?
upvoted 0 times
...
Tracey
7 days ago
C) Update the risk management plan. Duh, that's project management 101. Didn't they teach you that in your fancy certification course?
upvoted 0 times
...
Marisha
17 days ago
B) Review the effectiveness of the risk process. Gotta find out where things went wrong and learn from it. Hindsight is 20/20, right?
upvoted 0 times
Catalina
4 days ago
D) Escalate the project risks to upper management.
upvoted 0 times
...
Rosalyn
5 days ago
C) Update the risk management plan.
upvoted 0 times
...
Tiffiny
7 days ago
B) Review the effectiveness of the risk process.
upvoted 0 times
...
Luisa
12 days ago
A) Create a new project plan including the new risks.
upvoted 0 times
...
...
Tayna
22 days ago
I believe escalating the project risks to upper management is the best option. They need to be aware of the situation.
upvoted 0 times
...
Galen
25 days ago
I agree with Francis. It's important to see if there are any gaps in the risk management plan.
upvoted 0 times
...
Mable
26 days ago
D) Escalate the project risks to upper management. That's the obvious choice here. Can't let those executives off the hook, you know?
upvoted 0 times
Ricarda
7 days ago
B) Review the effectiveness of the risk process.
upvoted 0 times
...
Kayleigh
7 days ago
C) Update the risk management plan.
upvoted 0 times
...
Alpha
8 days ago
A) Create a new project plan including the new risks.
upvoted 0 times
...
...
Francis
26 days ago
I think the risk manager should review the effectiveness of the risk process.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77