Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 2 Question 79 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 79
Topic #: 2
[All PMI-RMP Questions]

You are the project manager for your organization. You have determined that an activity is too dangerous to complete internally so you hire licensed contractor to complete the work. The contractor, however, may not complete the assigned work on time which could cause delays in subsequent work beginning. This is an example of what type of risk event?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Kayleigh
6 months ago
Haha, I bet the contractor is just taking a nice long lunch break instead of doing the work. D. Transference is the way to go on this one!
upvoted 0 times
Yuonne
5 months ago
Transferring the risk to the contractor was the right move. D) Transference was the way to go.
upvoted 0 times
...
Skye
5 months ago
It's frustrating when contractors don't meet deadlines. D) Transference is definitely the right choice here.
upvoted 0 times
...
Quentin
5 months ago
I agree, the contractor seems to be slacking off. D) Transference is the best option in this situation.
upvoted 0 times
...
...
Gilma
6 months ago
C. Pure risk. Clearly the project manager is trying to avoid the pure risk of the dangerous activity by hiring the contractor.
upvoted 0 times
...
Marva
6 months ago
Hmm, I'm torn between B and D. Guess I'll have to go with my gut and say D. Transference. Hoping I don't get a risky result on this one!
upvoted 0 times
...
Paola
6 months ago
I agree with Ernestine. By hiring a contractor, we are transferring the risk of delays to them.
upvoted 0 times
...
Lizette
6 months ago
B. Secondary risk seems like the right answer here. The contractor not completing the work on time could lead to delays in other activities.
upvoted 0 times
...
Anthony
6 months ago
I think the answer is D. Transference. The project manager is transferring the risk of the dangerous work to the licensed contractor.
upvoted 0 times
Lashon
5 months ago
That's right. By hiring the contractor, the project manager is transferring the risk of the dangerous work.
upvoted 0 times
...
Jolanda
5 months ago
Yes, you are correct. The project manager is transferring the risk to the contractor.
upvoted 0 times
...
Rodrigo
6 months ago
That's correct. It's a form of risk transference in this situation.
upvoted 0 times
...
Colette
6 months ago
That's right, by hiring a licensed contractor, the project manager is transferring the risk to them.
upvoted 0 times
...
Jeannetta
6 months ago
Transference is the right answer because the project manager is shifting the risk to someone else.
upvoted 0 times
...
Gail
6 months ago
Yes, you're right. The project manager is transferring the risk to the contractor.
upvoted 0 times
...
Yolando
6 months ago
Yes, you are correct. The project manager is transferring the risk to the contractor.
upvoted 0 times
...
Mireya
6 months ago
That's right. By hiring a licensed contractor, the project manager is transferring the risk of the dangerous work to them.
upvoted 0 times
...
Kendra
6 months ago
Yes, you are correct. The project manager is transferring the risk to the contractor.
upvoted 0 times
...
...
Ernestine
6 months ago
I think the answer is D) Transference.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77