PMI Exam PMI-RMP Topic 8 Question 68 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 68
Topic #: 8
[All PMI-RMP Questions]

You are the project manager for your organization. You have determined that an activity is too dangerous to complete internally so you hire licensed contractor to complete the work. The contractor, however, may not complete the assigned work on time which could cause delays in subsequent work beginning. This is an example of what type of risk event?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Cammy
8 months ago
Haha, welcome to the world of project management, where the questions are tricky and the answers are never black and white! I think I'm going to go with D) Transference. Even though the contractor's delay is a secondary risk, the initial risk of the dangerous activity was transferred to them. Gotta play it safe on these certification exams, you know?
upvoted 0 times
...
Lorean
8 months ago
You know, I was stuck between C) Pure risk and D) Transference. Pure risk events are out of your control, and hiring the contractor is a way to transfer that risk. But I guess you could say the contractor's potential delay is a secondary risk. This question is really making my head spin!
upvoted 0 times
...
Nenita
8 months ago
I'm not so sure about that. I was leaning more towards B) Secondary risk. The delayed work from the contractor could cause issues with subsequent tasks, which seems like a secondary risk event to me. But I can see the argument for transference as well.
upvoted 0 times
Ilda
7 months ago
Great, I'm glad we could come to a consensus. Secondary risk it is!
upvoted 0 times
...
Daniel
7 months ago
Alright, I'm convinced. I think B) Secondary risk makes the most sense in this situation.
upvoted 0 times
...
Tu
8 months ago
That's a good point. I think the primary risk is the dangerous activity, and the delay from the contractor is a secondary risk.
upvoted 0 times
...
Mirta
8 months ago
But wouldn't the primary risk be the dangerous activity itself? In that case, wouldn't this situation be considered a secondary risk?
upvoted 0 times
...
Johnetta
8 months ago
I agree with B) Secondary risk. It seems like the delayed work from the contractor is causing a secondary risk to the project.
upvoted 0 times
...
Lakeesha
8 months ago
I see what you're saying, but I still think it's B) Secondary risk. The delay in the contractor's work could definitely impact other tasks.
upvoted 0 times
...
Selma
8 months ago
I think the correct answer is D) Transference. By hiring the contractor, you are transferring the risk of completing the dangerous activity to them.
upvoted 0 times
...
...
Daniel
8 months ago
Hmm, this is a tricky one. I think the correct answer is D) Transference. By hiring the licensed contractor, you're transferring the risk of the dangerous activity to them. If they don't complete the work on time, that's a secondary risk, but the initial risk was transferred from the organization to the contractor.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77