Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 1 Question 14 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 14
Topic #: 1
[All PMI-SP Questions]

Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.

Show Suggested Answer Hide Answer
Suggested Answer: A, C, D

The outputs to the determine budget process are as follows:

Cost performance baseline: The cost performance baseline is an authorized time-phased budget at

completion.

Project funding requirements: The project funding requirements are determined from total funding

requirements and periodic funding

requirements.

Project document updates: The project document updates consists of risk register, cost estimates

and project schedule.

Answer option B is incorrect. Scope baseline is an input to the determine budget process.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77