Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 1 Question 15 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 15
Topic #: 1
[All PMI-SP Questions]

You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project's budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?

Show Suggested Answer Hide Answer
Suggested Answer: B

Your schedule variance is -$33,750. You can find this by using the formula earned value-

minus planned.

Answer option C is incorrect. Cost is not the largest variance in the project.

Answer option A is incorrect. Cost is not the largest variance in the project (it is -$8,000).

Answer option D is incorrect. -$20,000 is the variance at completion for the project.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77