Which of the following is NOT an output of the control schedule process?
The project termination request is not an output of the control schedule. Early
termination of a project is a closing process and usually does
not stem from the project manager.
The outputs of the control schedule process are as follows:
Work Performance Measurements: The work packages and control accounts are documented and
communicated to the stakeholders.
Organizational Process Assets Updates: The assets that are updated are: corrective actions chosen
and the reasons, causes of
variance, and other types of lessons learned from project schedule control.
Change Requests: It is processed for reviews and disposition through the Perform Integrated Change
Control process.
Project Management Plan Updates: The elements that need to be updated are: schedule baseline,
schedule management plan, cost
baseline.
Project Document Updates: The elements that need to be updated in project document updates are:
schedule data and project
schedule.
Von
8 months agoBernadine
8 months agoChuck
8 months agoVeta
8 months agoBeth
7 months agoJonell
8 months agoRasheeda
8 months agoKerry
8 months agoSharen
8 months agoElbert
8 months ago