Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 2 Question 16 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 16
Topic #: 2
[All PMI-SP Questions]

Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?

Show Suggested Answer Hide Answer
Suggested Answer: D

This is an example of corrective action. The project team will fix the mistake and they

have learned from their mistake so it won't happen again.

Answer option C is incorrect. Risk mitigation is defined as monies spent or actions taken to reduce

the probability and impact of an identified

risk event.

Answer option A is incorrect. A risk response is an action to counteract an identified risk.

Answer option B is incorrect. There may be some team development happening in this instance but

we don't have enough information to know

for certain. Team development is an activity that brings the whole team cohesion, interdependency,

and trust.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77