Examine the figure given below.
In this project network diagram, what is the total float for Activity I?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Jillian
6 months agoNina
6 months agoJonell
7 months agoElise
7 months agoMicaela
7 months agoJillian
7 months ago