You are the project manager for the NHQ project. The management has reminded you that you must

not allocate any project team member for more than 25 hours per work week on your project. This

policy is because your organization is in a weak matrix and the project team members are on several

projects at once within the organization. The 25-hour limit per resource is an example of which one

of the following?

Show Suggested Answer Hide Answer
Suggested Answer: B

The limit on each work is an organizational policy for each project. Policies, rules, and

organizational requirements are the enterprise

environmental factors.

Answer option D is incorrect. Organizational process assets are things that have been created for the

project manager, such as software,

templates, guidelines, and other resources that will assist the project manager in completing the

project.

Answer option C is incorrect. While this could be a resource limitation, it is not a valid project

management term. Resource leveling heuristics

or a project constraint would have been acceptable answers.

Answer option A is incorrect. Expert judgment happens, when the project manager relies on

someone with more knowledge on a topic to help

the project manager make the best project decision.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77