Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 5 Question 8 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 8
Topic #: 5
[All PMI-SP Questions]

You are the project manager of the NHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day for the early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but you must be careful not to increase project risk beyond an acceptable level of risk exposure. Which of the following approaches is most likely to increase project risk?

Show Suggested Answer Hide Answer
Suggested Answer: D

Fast tracking allows entire phases of the project to overlap and this action does

increase risks. This is an approach that you would want to

avoid in your project.

Answer option B is incorrect. Crashing adds labor to the project and typically drives project costs.

Answer option A is incorrect. The critical chain method considers the availability of project resources

as part of its network diagramming

technique.

Answer option C is incorrect. Lead time allows project activities to overlap and may introduce

project risks, but not to the extent of using fast

tracking.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77