PMI Exam PMI-SP Topic 5 Question 90 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 90
Topic #: 5
[All PMI-SP Questions]

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You reviewed these activities with your project team and discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You elect to create a new schedule for the project. What project anagement process are you working with when you create a new target schedule?

Show Suggested Answer Hide Answer
Suggested Answer: C

In severe cases, new schedule duration estimates with new forecasted start and finish

dates are needed. In these instances, it is an example

of using the control schedule process.

Control schedule process is a method of monitoring the status of the project to update project

progress and deal with the changes to the

schedule baseline. It is concerned with:

Determining the current status of the project

Influencing the factors that create schedule changes

Determining that the project schedule has changed

Managing the actual changes as they occur

Control schedule is a component of the Perform Integration Change Control process.

Answer option D is incorrect. The activity resources would only address the addition or replacement

of resources needed to complete the

project work.

Answer option B is incorrect. This is a tempting choice, but new schedules are a part of the control

schedule process.

Answer option A is incorrect. Develop schedule is not the best choice for this question.


Contribute your Thoughts:

Flo
2 months ago
I'm not sure, but it makes sense that it would be Develop schedule. The current schedule needs to be adjusted to reflect the actual completion times of activities.
upvoted 0 times
...
Glen
2 months ago
I agree with Honey. When you create a new target schedule, you are working with the Develop schedule process.
upvoted 0 times
...
Micaela
2 months ago
D) Estimate activity resources? Really? I think that's a bit too specific for this question. My money's on A) Develop schedule.
upvoted 0 times
Elinore
1 months ago
Yeah, A) Develop schedule is definitely the right project management process for creating a new target schedule.
upvoted 0 times
...
Audry
1 months ago
I think A) Develop schedule makes the most sense in this situation.
upvoted 0 times
...
Mireya
2 months ago
C) Control schedule might also be a possibility, but I agree that A) Develop schedule is the best choice.
upvoted 0 times
...
Fallon
2 months ago
A) Develop schedule is the correct answer. It involves creating a new target schedule.
upvoted 0 times
...
...
Tiera
2 months ago
Ha! I bet the project team is secretly hoping for a longer schedule. More time to goof off, am I right? Anyway, I'm going with A) Develop schedule.
upvoted 0 times
Mirta
2 months ago
I think the project team would definitely appreciate a longer schedule, but for now, focusing on creating a new schedule is the way to go. A) Develop schedule it is.
upvoted 0 times
...
Kris
2 months ago
Creating a new target schedule is definitely part of the Develop schedule process. Good choice!
upvoted 0 times
...
Makeda
2 months ago
Yes, you're right! A longer schedule would definitely give them more time to goof off. I agree with you, it's A) Develop schedule.
upvoted 0 times
...
...
Raul
3 months ago
Hmm, I'm not too sure about this one. I was thinking it could be C) Control schedule, since we're trying to get the project back on track.
upvoted 0 times
Felix
1 months ago
D) Estimate activity resources
upvoted 0 times
...
Kirby
2 months ago
C) Control schedule
upvoted 0 times
...
Candida
2 months ago
B) Estimate activity durations
upvoted 0 times
...
Cyndy
2 months ago
A) Develop schedule
upvoted 0 times
...
...
Honey
3 months ago
I think the answer is A) Develop schedule.
upvoted 0 times
...
Annamae
3 months ago
I think the correct answer is A) Develop schedule. We're creating a new target schedule, which is part of the Develop Schedule process.
upvoted 0 times
Stephen
2 months ago
That's correct. When creating a new target schedule, we are indeed working with the Develop Schedule process.
upvoted 0 times
...
Providencia
2 months ago
A) Develop schedule
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77