You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project's budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?
Your schedule variance is -$33,750. You can find this by using the formula earned value-
minus planned.
Answer option C is incorrect. Cost is not the largest variance in the project.
Answer option A is incorrect. Cost is not the largest variance in the project (it is -$8,000).
Answer option D is incorrect. -$20,000 is the variance at completion for the project.
Shalon
2 months agoVonda
2 months agoSheldon
7 days agoArgelia
8 days agoVivienne
9 days agoElinore
23 days agoEstrella
24 days agoJerry
28 days agoGlenn
1 months agoLoreta
2 months agoChaya
2 months agoColton
1 months agoTaryn
1 months agoDyan
2 months agoDevon
2 months agoCasey
2 months agoCyril
1 months agoLettie
1 months agoPaulina
2 months agoLigia
2 months agoLoreta
3 months ago