PMI Exam PMI-SP Topic 5 Question 91 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 91
Topic #: 5
[All PMI-SP Questions]

You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project's budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?

Show Suggested Answer Hide Answer
Suggested Answer: B

Your schedule variance is -$33,750. You can find this by using the formula earned value-

minus planned.

Answer option C is incorrect. Cost is not the largest variance in the project.

Answer option A is incorrect. Cost is not the largest variance in the project (it is -$8,000).

Answer option D is incorrect. -$20,000 is the variance at completion for the project.


Contribute your Thoughts:

Shalon
2 months ago
I'm going with C. The cost variance of $278,000 is definitely the largest and most significant issue here.
upvoted 0 times
...
Vonda
2 months ago
Haha, this is like a trick question! I bet the project manager is sweating bullets trying to figure this out.
upvoted 0 times
Sheldon
7 days ago
Vivienne: That would make sense, covering all bases for the variance report.
upvoted 0 times
...
Argelia
8 days ago
User 3: Maybe it's both, cost with a variance of $278,000 and schedule with a variance of -$33,750.
upvoted 0 times
...
Vivienne
9 days ago
User 2: No, I believe it's in schedule, with a variance of -$33,750.
upvoted 0 times
...
Elinore
23 days ago
C) Cost, with a variance of $278,000
upvoted 0 times
...
Estrella
24 days ago
B) Schedule, with a variance of -$33,750
upvoted 0 times
...
Jerry
28 days ago
User 1: I think the largest variance is in cost, with a variance of $278,000.
upvoted 0 times
...
Glenn
1 months ago
A) Cost, with a variance of -$8,000
upvoted 0 times
...
...
Loreta
2 months ago
True, but the cost variance of $278,000 is the biggest issue here.
upvoted 0 times
...
Chaya
2 months ago
Hmm, I'm not sure. The schedule variance seems important too. Maybe B is the right answer?
upvoted 0 times
Colton
1 months ago
Yeah, the cost variance is definitely the largest.
upvoted 0 times
...
Taryn
1 months ago
I agree, option C shows a variance of $278,000.
upvoted 0 times
...
Dyan
2 months ago
I think the cost variance is the largest.
upvoted 0 times
...
...
Devon
2 months ago
But the schedule variance is also significant.
upvoted 0 times
...
Casey
2 months ago
I think the answer is C. The question states the project has spent $278,000 of the budget, which is a cost variance.
upvoted 0 times
Cyril
1 months ago
The schedule variance options are negative, so they can't be the largest.
upvoted 0 times
...
Lettie
1 months ago
But what about the schedule variance options?
upvoted 0 times
...
Paulina
2 months ago
I agree, it makes sense that the cost variance would be the largest.
upvoted 0 times
...
Ligia
2 months ago
I think the answer is C.
upvoted 0 times
...
...
Loreta
3 months ago
I think the largest variance is in cost.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77