Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 6 Question 80 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 80
Topic #: 6
[All PMI-SP Questions]

Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:

If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Shawnee
5 months ago
Hmm, I don't know about you, but I'm always a little suspicious when the project schedule is 'fixed and cannot vary'. Maybe Mary needs to brush up on her risk management skills.
upvoted 0 times
...
Hyman
5 months ago
That's true, but if Stephen's assignment is critical, it could delay the whole project.
upvoted 0 times
...
Tracie
5 months ago
But the project schedule is fixed, so it will be late by one day.
upvoted 0 times
...
Pedro
5 months ago
Wow, this is a tough one. I was tempted to go with B, but after looking at the diagram, it's clear that C is the right answer. No shortcuts here, folks!
upvoted 0 times
Nieves
4 months ago
Definitely, every team member's contribution is crucial to the success of the project.
upvoted 0 times
...
Dorathy
4 months ago
So, it's important for Stephen to try and catch up to avoid delaying the entire project.
upvoted 0 times
...
Maybelle
4 months ago
Yes, the critical path clearly shows that any delay in Activity B will directly impact the project end date.
upvoted 0 times
...
Pete
5 months ago
I agree, looking at the diagram makes it clear that the project will be late by two days.
upvoted 0 times
...
...
Hyman
5 months ago
I think Stephen's delay will make the project late by two days.
upvoted 0 times
...
Marvel
5 months ago
Haha, looks like Stephen needs to work on his time management skills. At least he's being honest about the delay, right? But C is the correct answer here.
upvoted 0 times
...
Edison
5 months ago
I agree with Verona. The project schedule is fixed, and Stephen's two-day delay in completing Activity B will push the entire project completion by two days.
upvoted 0 times
Arlene
4 months ago
I think Mary should reassign some resources to help Stephen finish his task on time.
upvoted 0 times
...
Tamesha
4 months ago
Stephen should try to catch up on his work to avoid delaying the project.
upvoted 0 times
...
...
Verona
6 months ago
The project will be late by two days. Activity B is on the critical path, so any delay in that activity will directly impact the project end date.
upvoted 0 times
Roslyn
5 months ago
Let's see if we can allocate more resources to Activity B to get it back on track.
upvoted 0 times
...
German
5 months ago
Stephen, we need to find a way to speed up Activity B. It's on the critical path and any delay will make the project late.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77