Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:
If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?
Shawnee
5 months agoHyman
5 months agoTracie
5 months agoPedro
5 months agoNieves
4 months agoDorathy
4 months agoMaybelle
4 months agoPete
5 months agoHyman
5 months agoMarvel
5 months agoEdison
5 months agoArlene
4 months agoTamesha
4 months agoVerona
6 months agoRoslyn
5 months agoGerman
5 months ago