PMI Exam PMI-SP Topic 7 Question 11 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 11
Topic #: 7
[All PMI-SP Questions]

Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?

Show Suggested Answer Hide Answer
Suggested Answer: C

The estimate at completion (EAC) formula is the Budget at Completion (BAC)/Cost

Performance Index (CPI). In this instance, the CPI is .78 and

the BAC is $344,000. Cathy's project isn't doing too well.

Answer option D is incorrect. This value represents the estimate to complete for the project.

Answer option B is incorrect. This value represents the negative cost variance.

Answer option A is incorrect. This value represents the negative value the project will have once all

the work is completed.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77