Harry works as a project manager for BlueWell Inc. He is determining the budget of the project.

According to the PMBOK, there are seven

inputs to this process. Which one of the following is NOT an input to the determine budget process?

Show Suggested Answer Hide Answer
Suggested Answer: B

Reserve analysis is not an input to the determine budget process. It is a technique used

for determining the budget.

The inputs to the determine budget process are as follows:

Activity cost estimates

Basis of estimates

Scope baseline

Project schedule

Resource calendars

Contracts

Organizational process assets


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77