Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 7 Question 51 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 51
Topic #: 7
[All PMI-SP Questions]

You work as the project manager for BlueWell Inc. Mark, a project team member, has some doubts

related to the outputs of the control

schedule process. Which of the following is an output of the control schedule process?

Show Suggested Answer Hide Answer
Suggested Answer: C

Only change request is a valid answer. The five outputs of the control schedule process

are work performance measurements, organizational

process assets updates, change requests, the project management plan updates, and project

document updates.

Change requests are requests to expand or reduce the project scope, modify policies, processes,

plans, or procedures, modify costs or

budgets or revise schedules. These requests for a change can be direct or indirect, externally or

internally initiated, and legally or contractually

imposed or optional. A Project Manager needs to ensure that only formally documented requested

changes are processed and only approved

change requests are implemented.

Answer option D is incorrect. Activity resource requirement is not an output of the control schedule

process.

Answer option A is incorrect. The project schedule is not an output of the control schedule process.

Answer option B is incorrect. Lessons learned is not an output of the control schedule process.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77