Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 8 Question 54 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 54
Topic #: 8
[All PMI-SP Questions]

Which of the following provides a method to track project progress during project execution against what was planned?

Show Suggested Answer Hide Answer
Suggested Answer: C

A schedule baseline provides a method to track project progress during project

execution against what was planned.

What is schedule baseline?

Schedule baseline is a project schedule used in measuring project progress. It helps provide a

comparison with the actual

progress of work against the schedule and to determine if performance to date is within acceptable

parameters. Any

change caused by change in scope of the project invalidates the original schedule and requires a new

baseline schedule.

Answer options D, A, and B are incorrect. A detailed project budget, team members profile, and

benefit-cost ratio will not help you track

project progress.

What is BCR?

A benefit-cost ratio (BCR) is an indicator, used in the formal discipline of cost-benefit analysis, that

attempts to summarize

the overall value for money of a project or proposal. A BCR is the ratio of the benefits of a project or

proposal, expressed in

monetary terms, relative to its costs, also expressed in monetary terms. All benefits and costs should

be expressed in

discounted present values. For e.g., a BCR of $3.8 indicates a payback of $3.8 for each dollar

expended.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77