Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 1 Question 49 Discussion

Actual exam question for PMI's PMP exam
Question #: 49
Topic #: 1
[All PMP Questions]

A project team is executing a megaproject, and several contract requirements have been identified. In the planning phase, the project team agreed that a contract would be

required 3 months prior to the project's finish date. During project execution, it was determined that the contract was required immediately.

What should project manager do?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77