PMI Exam PMP Topic 1 Question 87 Discussion

Actual exam question for PMI's PMP exam
Question #: 87
Topic #: 1
[All PMP Questions]

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Elouise
2 months ago
D all the way! You gotta be a problem-solver, not a problem-maker. Get those stakeholders to see eye-to-eye and watch the project fly.
upvoted 0 times
...
Sanjuana
2 months ago
Option A? Really? Sounds more like a recipe for disaster than a solution. Jumping in without addressing the underlying issues? Not my cup of tea.
upvoted 0 times
Candra
20 days ago
True, option A might lead to more problems. Addressing the root cause seems like a better approach.
upvoted 0 times
...
Miles
28 days ago
D) Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.
upvoted 0 times
...
Tien
1 months ago
B) Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.
upvoted 0 times
...
Luis
1 months ago
A) Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control
upvoted 0 times
...
...
Lavonna
2 months ago
Hah, cancel the project? Good one! C is about as useful as a chocolate teapot. Might as well just throw in the towel and go home.
upvoted 0 times
Margery
19 days ago
D) Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.
upvoted 0 times
...
Arlen
21 days ago
B) Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.
upvoted 0 times
...
Bette
23 days ago
A) Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control
upvoted 0 times
...
...
Vanda
2 months ago
I believe option B could also be effective. Inviting stakeholders to a CCB meeting can help address conflicts and misunderstandings.
upvoted 0 times
...
Roxane
3 months ago
D for sure! You gotta get to the root of the problem and make sure everyone's on the same page. Anything less and you're just putting a bandaid on a broken leg.
upvoted 0 times
...
Lorenza
3 months ago
I agree with Melinda. Determining the root cause and getting all parties to reach a consensus is crucial for the project's success.
upvoted 0 times
...
Dulce
3 months ago
I think option B is the way to go. Get all those stakeholders in a room, hash out the issues, and come to a consensus. After all, communication is key to keeping a project on track.
upvoted 0 times
Alex
2 months ago
Absolutely, communication is key in resolving conflicts and ensuring the project stays on track.
upvoted 0 times
...
Lashaunda
2 months ago
D) Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.
upvoted 0 times
...
Ammie
2 months ago
B) Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.
upvoted 0 times
...
Georgene
2 months ago
A) Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control
upvoted 0 times
...
...
Melinda
3 months ago
I think the project manager should choose option D.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77