PMI Exam PMP Topic 2 Question 81 Discussion

Actual exam question for PMI's PMP exam
Question #: 81
Topic #: 2
[All PMP Questions]

Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Rolande
5 months ago
Haha, sounds like this project team member is a real maverick, increasing the scope without approval. I hope the project manager has a good handle on this wild ride!
upvoted 0 times
Thaddeus
3 months ago
D) Update project documentation with the new scope
upvoted 0 times
...
Tayna
3 months ago
C) Evaluate the impacts of the changes that were made to the project
upvoted 0 times
...
Therese
3 months ago
A) Remove the changes to match the original requirements.
upvoted 0 times
...
Kaitlyn
4 months ago
D) Update project documentation with the new scope
upvoted 0 times
...
Frank
4 months ago
C) Evaluate the impacts of the changes that were made to the project
upvoted 0 times
...
Rolland
4 months ago
A) Remove the changes to match the original requirements.
upvoted 0 times
...
Mindy
4 months ago
D) Update project documentation with the new scope
upvoted 0 times
...
Yun
4 months ago
C) Evaluate the impacts of the changes that were made to the project
upvoted 0 times
...
...
Gladys
5 months ago
Updating project documentation with the new scope is also crucial for transparency and accountability.
upvoted 0 times
...
Gregoria
5 months ago
Adding team members might help with schedule delays, but we need to first assess the impacts of the changes.
upvoted 0 times
...
Adelle
5 months ago
I agree with Hector, it's important to understand the consequences of the increased scope.
upvoted 0 times
...
Hector
5 months ago
I think the project manager should evaluate the impacts of the changes that were made to the project.
upvoted 0 times
...
Tammara
5 months ago
Updating the project documentation is also important, but that should be done after the impacts have been evaluated. Can't put the cart before the horse!
upvoted 0 times
...
Marti
5 months ago
I agree with Pete. C is the correct answer here. Trying to remove the changes or add more team members without understanding the full impact would be a mistake.
upvoted 0 times
Casie
4 months ago
Agreed, it's important to understand the full impact before taking any action.
upvoted 0 times
...
Edna
5 months ago
I think we should evaluate the impacts of the changes before making any decisions.
upvoted 0 times
...
...
Pete
6 months ago
The project manager should definitely evaluate the impacts of the changes to the project. That's the only way to determine the best course of action.
upvoted 0 times
Sabine
5 months ago
D) Update project documentation with the new scope
upvoted 0 times
...
Theodora
5 months ago
C) Evaluate the impacts of the changes that were made to the project
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77