Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam Questions

Exam Name: PMI Scheduling Professional
Exam Code: PMI-SP
Related Certification(s): PMI Scheduling Professional PMI-SP Certification
Certification Provider: PMI
Actual Exam Duration: 120 Minutes
Number of PMI-SP practice questions in our database: 326 (updated: Dec. 12, 2024)
Expected PMI-SP Exam Topics, as suggested by PMI :
  • Topic 1: Collect resource information and updates via reports, timesheets, meetings, inspections/ Develop the project resource breakdown structure (RBS)
  • Topic 2: Identify critical and near-critical path(s) using techniques such as Critical Path Method/ Establish scheduling policies and procedures regarding methodology
  • Topic 3: Define activities and milestones through communication with subject matter experts/ Develop the scheduling-related components for project management plans
  • Topic 4: Perform schedule analysis and audit, on in-house and subcontractor schedules/ Provide information about project scheduling objectives and goals
  • Topic 5: Establish project schedule configuration management policies and procedures incorporating best practices/ Align schedule with the overall program plan or integrated master plan (IMP)
  • Topic 6: Obtain a consensus of the project customer, sponsor, project manager/ Update the schedule model and document schedule baseline changes
  • Topic 7: Develop schedule approach, based on the unique characteristics of the project/ Incorporate approved risk mitigation activities into the schedule
  • Topic 8: Collect activity status at defined intervals from activity owners via reports, meetings, inspections/ Sequence activities, incorporating defined dependencies Perform schedule risk analysis using quantitative tools or techniques/ Analyze major milestones against statement of work (SOW)
  • Topic 9: Adjust schedule model based upon resource availability/ Establish the Performance Measurement Baseline (PMB)
Disscuss PMI PMI-SP Topics, Questions or Ask Anything Related

Una

2 days ago
I successfully passed the PMI Scheduling Professional exam, and the Pass4Success practice questions were a great help. One question that caught me off guard was about the tools and techniques for schedule monitoring and controlling. I wasn't sure which tool to choose, but I passed anyway.
upvoted 0 times
...

Tegan

3 days ago
Thrilled to have passed the PMI-SP exam! Pass4Success provided relevant questions that really prepared me well.
upvoted 0 times
...

Darell

5 days ago
The exam had several questions on schedule network analysis. Make sure you understand forward and backward pass calculations, and how to interpret network diagrams.
upvoted 0 times
...

Jesusa

17 days ago
Happy to announce that I passed the PMI Scheduling Professional exam. The Pass4Success practice questions were very useful. There was a question on how to develop a Work Breakdown Structure (WBS) for schedule planning. I found it challenging but still passed.
upvoted 0 times
...

Joaquin

18 days ago
Be prepared for scenario-based questions on schedule compression techniques. Know when to use fast-tracking vs. crashing and their potential risks.
upvoted 0 times
...

Novella

1 months ago
Passed my PMI-SP certification! Pass4Success's exam questions were a lifesaver for last-minute studying.
upvoted 0 times
...

Sage

1 months ago
I passed the PMI Scheduling Professional exam, thanks to the Pass4Success practice questions. One question that puzzled me was about the best practices for stakeholder communication in schedule management. I wasn't certain of the correct answer, but I managed to pass.
upvoted 0 times
...

Wenona

1 months ago
Earned Value Management (EVM) is heavily tested. Practice calculating CPI, SPI, and forecasting final costs. Pass4Success really helped me master these concepts quickly!
upvoted 0 times
...

Micheal

2 months ago
Thrilled to share that I passed the PMI Scheduling Professional exam. The Pass4Success practice questions were spot on. One challenging question asked about the steps involved in closing out a project schedule. I was unsure about the sequence, but I still succeeded.
upvoted 0 times
...

Hester

2 months ago
Heads up on resource leveling questions. They often ask about techniques to optimize resource allocation across multiple projects. Study different leveling strategies and their impacts.
upvoted 0 times
...

Kris

2 months ago
Wow, the PMI Scheduling Professional exam was tough, but I made it! Grateful for Pass4Success's quick prep materials.
upvoted 0 times
...

Armando

2 months ago
Just passed the PMI Scheduling Professional exam! The Pass4Success practice questions were a lifesaver. There was a tricky question on how to monitor schedule performance using Earned Value Management (EVM). I wasn't confident in my answer, but I still made it through.
upvoted 0 times
...

Danica

3 months ago
Just passed the PMI-SP exam! The questions on critical path method were tricky. Make sure you can calculate float and identify critical activities. Thanks Pass4Success for the great prep materials!
upvoted 0 times
...

Nadine

3 months ago
I recently passed the PMI Scheduling Professional exam, and I must say, the Pass4Success practice questions were incredibly helpful. One question that stumped me was about developing a Schedule Management Plan. It asked how to integrate risk management into the schedule planning process. I wasn't entirely sure of the best approach, but I managed to pass the exam nonetheless.
upvoted 0 times
...

Jonell

3 months ago
Just passed the PMI-SP exam! Pass4Success's practice questions were spot-on. Thanks for helping me succeed!
upvoted 0 times
...

Flo

4 months ago
Successfully passing the PMI Scheduling Professional exam was a great achievement for me, and I attribute my success to the thorough preparation I did with Pass4Success practice questions. One question that I remember from the exam was about developing the project resource breakdown structure (RBS). It tested my knowledge of how to organize and categorize project resources to ensure efficient resource allocation and utilization throughout the project lifecycle.
upvoted 0 times
...

Barabara

5 months ago
My experience taking the PMI Scheduling Professional exam was a success, as I passed with flying colors using Pass4Success practice questions. The exam covered a wide range of topics, including developing the project resource breakdown structure and establishing scheduling policies. One question that I found particularly tricky was about collecting resource information and updates via reports, timesheets, meetings, and inspections. It required me to demonstrate my understanding of how to effectively gather and utilize resource data for project scheduling purposes.
upvoted 0 times
...

Anglea

5 months ago
Just passed the PMI-SP exam! Critical path analysis was a key focus. Expect questions on float calculation and schedule compression techniques. Brush up on your network diagramming skills. Thanks to Pass4Success for the spot-on practice questions that helped me prepare efficiently!
upvoted 0 times
...

Flo

6 months ago
I passed the PMI Scheduling Professional exam with the help of Pass4Success practice questions. The exam was challenging, but I felt well-prepared thanks to the detailed explanations provided in the practice questions. One question that stood out to me was related to identifying critical paths using the Critical Path Method. It required me to analyze a complex project schedule and determine the sequence of tasks that would impact the project timeline the most.
upvoted 0 times
...

Free PMI PMI-SP Exam Actual Questions

Note: Premium Questions for PMI-SP were last updated On Dec. 12, 2024 (see below)

Question #1

with the appropriate word. When activities are logically linked, they become the .

__________

Reveal Solution Hide Solution
Correct Answer: A

An activity is an individual element of work that is logically linked to other activities to

form the schedule. Its primary characteristics include an overall duration based upon the resources

applied to it (manpower, material, and equipment), as well as a start and

completion date that is tied to a work calendar. It also has a relationship with other activities

(predecessors and successors).


Question #2

Harry is the project manager of a large network installation project. This project requires Harry to

add network cable to each office and cubicle of a 14-story office building. Harry will receive a bonus

for good time and cost performance in this project. What law of economics would prevent Harry

from exponentially adding labor to the project work in an effort to complete the work in a very small

amount of time?

Reveal Solution Hide Solution
Correct Answer: B

The law of diminishing returns state that the user cannot exponentially add labor to a

project to reduce the amount of time required to complete the project work. In other words, Harry

cannot keep doubling the workforce on this project to reduce the project duration down to

just a few minutes.

The law of diminishing returns state that 'the user will get less and less output when he add

additional doses of an input while holding other

inputs fixed. In other words, the marginal product of each unit of input will decline as the amount of

that input increases holding all other

inputs constant.' Diminishing returns mean that the extra labor causes output to fall, which means

that the MPL is negative. In other words,

the change in output per unit increase in labor is negative and total output is falling.

Answer option C is incorrect. This is not a valid project management term.

Answer option A is incorrect. Parkinson's Law states that work will expand to the amount of time

allotted to it.

Answer option D is incorrect. Moore's Law is based on Intel's Gordon Moore who stated that

processor speeds generally double in power

every 18 months.


Question #3

Examine the figure given below.

In this project network diagram, what is the total float for Activity I?

Reveal Solution Hide Solution
Correct Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Question #4

You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project's budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?

Reveal Solution Hide Solution
Correct Answer: B

Your schedule variance is -$33,750. You can find this by using the formula earned value-

minus planned.

Answer option C is incorrect. Cost is not the largest variance in the project.

Answer option A is incorrect. Cost is not the largest variance in the project (it is -$8,000).

Answer option D is incorrect. -$20,000 is the variance at completion for the project.


Question #5

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You reviewed these activities with your project team and discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You elect to create a new schedule for the project. What project anagement process are you working with when you create a new target schedule?

Reveal Solution Hide Solution
Correct Answer: C

In severe cases, new schedule duration estimates with new forecasted start and finish

dates are needed. In these instances, it is an example

of using the control schedule process.

Control schedule process is a method of monitoring the status of the project to update project

progress and deal with the changes to the

schedule baseline. It is concerned with:

Determining the current status of the project

Influencing the factors that create schedule changes

Determining that the project schedule has changed

Managing the actual changes as they occur

Control schedule is a component of the Perform Integration Change Control process.

Answer option D is incorrect. The activity resources would only address the addition or replacement

of resources needed to complete the

project work.

Answer option B is incorrect. This is a tempting choice, but new schedules are a part of the control

schedule process.

Answer option A is incorrect. Develop schedule is not the best choice for this question.



Unlock Premium PMI-SP Exam Questions with Advanced Practice Test Features:
  • Select Question Types you want
  • Set your Desired Pass Percentage
  • Allocate Time (Hours : Minutes)
  • Create Multiple Practice tests with Limited Questions
  • Customer Support
Get Full Access Now

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77