Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Agile-Foundation Topic 1 Question 47 Discussion

Actual exam question for PRINCE2's PRINCE2-Agile-Foundation exam
Question #: 47
Topic #: 1
[All PRINCE2-Agile-Foundation Questions]

Which well-known agile method uses visualization, and controls work in progress?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Florinda
5 months ago
You might be right, Dana. Pretty sure it's D) Kanban then.
upvoted 0 times
...
Colette
6 months ago
I think Kanban makes sense. They limit the tasks in each stage to avoid bottlenecks.
upvoted 0 times
...
Margo
6 months ago
Daily stand-ups are a good point, but they don't focus much on controlling work in progress.
upvoted 0 times
...
Florinda
6 months ago
Interesting point, I was considering Scrum because of the daily stand-ups.
upvoted 0 times
...
Tatum
6 months ago
I agree, but it sounds like Kanban to me. They use boards to visualize tasks.
upvoted 0 times
...
Margo
7 months ago
I think this one's tricky. Visualization and controlling work in progress, hmm...
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77