Question #: 76
Topic #: 1
[All PRINCE2-Practitioner Questions]

During the 'starting up a project' process, the project manager discusses the standard model for course development with the executive. The project manager then assesses how the Health and Safety Training Project will be delivered, including what products should be delivered in each stage.

Is this an appropriate way to carry out the 'plan the initiation stage' activity, and why?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Reynalda
2 months ago
Option A is the way to go, like a project manager jumping through hoops to get the green light. Gotta love bureaucracy!
upvoted 0 times
...
Louisa
2 months ago
Personally, I'd go for A. It's all about making sure the initiation stage is well-planned and approved, just like the rest of the project.
upvoted 0 times
Cruz
28 days ago
User 3: I think option A is the way to go, it ensures that the work of the initiation stage is properly planned and approved.
upvoted 0 times
...
Linwood
1 months ago
Definitely, it's important to have a well-planned and approved initiation stage.
upvoted 0 times
...
Jutta
1 months ago
I agree, option A seems like the right choice for planning the initiation stage.
upvoted 0 times
...
...
Catalina
2 months ago
Hmm, I'm not convinced by option D. The senior supplier's role is more about assessing the overall project approach, not just the initiation stage.
upvoted 0 times
Shenika
2 months ago
Hmm, I agree. Option D seems to focus more on the overall project approach rather than just the initiation stage.
upvoted 0 times
...
Julianna
2 months ago
B) Yes, because the management controls for the initiation stage need to be defined and approved by the project board.
upvoted 0 times
...
Dyan
2 months ago
A) Yes, because the work of the initiation stage needs to be planned and approved, in the same way as other project work.
upvoted 0 times
...
...
Benedict
2 months ago
I disagree. I think option C is the right answer because subsequent stages are planned as part of creating the project plan.
upvoted 0 times
...
Stefany
2 months ago
I'm going with C on this one. Subsequent stages should be planned as part of the project plan, not just the initiation stage.
upvoted 0 times
Isabella
1 months ago
D) No, because the senior supplier is responsible for assessing the viability of the project approach.
upvoted 0 times
...
Celestina
1 months ago
C) No, because subsequent stages are planned in the initiation stage as part of creating the project plan.
upvoted 0 times
...
Casey
2 months ago
B) Yes, because the management controls for the initiation stage need to be defined and approved by the project board.
upvoted 0 times
...
Franchesca
2 months ago
A) Yes, because the work of the initiation stage needs to be planned and approved, in the same way as other project work.
upvoted 0 times
...
...
Clorinda
2 months ago
I agree with Josephine. It's important to have a plan for the initiation stage before moving forward.
upvoted 0 times
...
Patria
3 months ago
Option B makes sense to me. Defining the management controls for the initiation stage is crucial before moving forward.
upvoted 0 times
Lynelle
2 months ago
Absolutely, it sets the foundation for the rest of the project.
upvoted 0 times
...
Marsha
2 months ago
Yes, it helps ensure that the project is on the right track from the beginning.
upvoted 0 times
...
Latonia
2 months ago
I agree, defining management controls in the initiation stage is important.
upvoted 0 times
...
...
Bobbie
3 months ago
Yes, I think option A is the way to go. Planning and approving the initiation stage is just as important as any other project work.
upvoted 0 times
Nan
3 months ago
Definitely, it sets the foundation for the rest of the project.
upvoted 0 times
...
Tijuana
3 months ago
I agree, planning the initiation stage is crucial for the success of the project.
upvoted 0 times
...
...
Josephine
3 months ago
I think option A is correct because the initiation stage work needs to be planned and approved.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77