Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 2 Question 49 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 49
Topic #: 2
[All PRINCE2-Practitioner Questions]

The project is now in stage 2. The 'training venue specifications' will not be delivered to schedule and the stage is forecast to exceed its time tolerance. As a result, the project manager has agreed with the team manager that the 'training venue specifications' will be delivered in stage 3 instead of stage 2.

Is this an appropriate action, and why?

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77