PRINCE2 Exam PRINCE2-Practitioner Topic 2 Question 73 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 73
Topic #: 2
[All PRINCE2-Practitioner Questions]

The senior user is concerned that the trainers' limited availability could delay their accreditation. This was discussed during the 'starting up a project' process, but during the 'initiating a project' process the project manager notices that it has not been recorded.

Which action should the project manager take FIRST?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Kimi
2 months ago
Haha, trainers' limited availability? Sounds like they need to get their acts together! I'd go with A) myself.
upvoted 0 times
...
Edgar
2 months ago
This question is a real brain-teaser! I'm gonna have to go with A) though. Gotta stay on top of those project plans, you know?
upvoted 0 times
Alton
1 months ago
Let's make sure we stay on top of those project plans to keep things running smoothly.
upvoted 0 times
...
Jesusa
1 months ago
It's important to add appropriate activities to the project plan to avoid any adverse impact.
upvoted 0 times
...
Carlee
1 months ago
I agree, A) seems like the best course of action to manage the concern.
upvoted 0 times
...
...
Lilli
2 months ago
B) An exception report? Really? Isn't that a bit drastic? I'd go with A) and proactively manage it.
upvoted 0 times
...
An
2 months ago
D) Hmm, I don't know. Putting it in the risk register seems a bit passive. I'd go with C) and get that issue report rolling.
upvoted 0 times
Sherill
1 months ago
I agree with Sherill, let's get that issue report rolling.
upvoted 0 times
...
Loise
1 months ago
Loise, I disagree. We should raise an issue report to allocate the trainers' time.
upvoted 0 times
...
Emogene
2 months ago
I think we should add the information to the risk register.
upvoted 0 times
...
...
Helene
2 months ago
Adding the information to the risk register could also help in evaluating the situation and taking necessary action.
upvoted 0 times
...
Bettina
3 months ago
I agree with Marti. It's important to avoid any adverse impact on the project.
upvoted 0 times
...
Marti
3 months ago
I think the project manager should add appropriate activities to the project plan to manage the concern.
upvoted 0 times
...
Glendora
3 months ago
A) Definitely the way to go! Get those activities added pronto before it becomes a bigger issue.
upvoted 0 times
Ulysses
1 months ago
A) Yes, it's crucial to take action now to ensure the project stays on track.
upvoted 0 times
...
Nichelle
2 months ago
C) Adding it to the risk register could also help in evaluating the impact of the trainers' availability.
upvoted 0 times
...
Vince
2 months ago
B) I agree, it's important to address this issue early on to prevent any delays.
upvoted 0 times
...
Cammy
2 months ago
A) Definitely the way to go! Get those activities added pronto before it becomes a bigger issue.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77