PRINCE2 Exam PRINCE2-Practitioner Topic 3 Question 65 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 65
Topic #: 3
[All PRINCE2-Practitioner Questions]

The project is approaching the end of stage 4 and all work will be completed as planned. The project manager is now preparing a plan for acceptance and the handover of the 'capability to provide health and safety training'.

Is this appropriate, and why?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Sherill
5 months ago
I'm gonna have to go with C on this one. Leaving closure planning until the end of stage 4 is definitely not best practice.
upvoted 0 times
Marvel
4 months ago
User acceptance should have been ongoing, not just at the end.
upvoted 0 times
...
Ammie
4 months ago
I agree, closure activities should have been planned earlier.
upvoted 0 times
...
...
Heike
6 months ago
Haha, maybe the project manager is just trying to make their job look more important by coming up with a 'plan for acceptance and handover' at the last minute.
upvoted 0 times
...
Hester
6 months ago
B is a bit strange. Why would you create a separate closure stage plan during stage 4? Seems like unnecessary bureaucracy to me.
upvoted 0 times
Markus
5 months ago
B) I agree, it does seem like unnecessary bureaucracy to create a separate closure stage plan during stage 4.
upvoted 0 times
...
Allene
5 months ago
B is a bit strange. Why would you create a separate closure stage plan during stage 4? Seems like unnecessary bureaucracy to me.
upvoted 0 times
...
Mendy
5 months ago
C) No, because closure activities should have been planned at the end of stage 3.
upvoted 0 times
...
Cornell
5 months ago
A) Yes, because a plan should be created to measure the number of courses carried out after project closure.
upvoted 0 times
...
Thersa
6 months ago
A) Yes, because a plan should be created to measure the number of courses carried out after project closure.
upvoted 0 times
...
...
Anastacia
6 months ago
D seems more appropriate to me. User acceptance should be an ongoing process throughout the project, not just at the very end.
upvoted 0 times
Alonso
5 months ago
I agree, user acceptance should have been happening throughout the project, not just at the end.
upvoted 0 times
...
Shalon
6 months ago
Yes, because a plan should be created to measure the number of courses carried out after project closure.
upvoted 0 times
...
Stanton
6 months ago
D seems more appropriate to me. User acceptance should be an ongoing process throughout the project, not just at the very end.
upvoted 0 times
...
...
Buck
6 months ago
I disagree. Closure activities should have been planned earlier in the project.
upvoted 0 times
...
Arthur
6 months ago
I agree with Teddy. It's important to have a clear plan for closure activities.
upvoted 0 times
...
Teddy
6 months ago
I think it's appropriate to prepare a plan for acceptance and handover at this stage.
upvoted 0 times
...
Glenn
6 months ago
I think the correct answer is C. Closure activities should have been planned at the end of stage 3, not in the middle of stage 4. It's too late to be creating a plan now.
upvoted 0 times
Annelle
5 months ago
No, because closure activities should have been planned at the end of stage 3, not in the middle of stage 4. It's too late to be creating a plan now.
upvoted 0 times
...
Theron
6 months ago
I think the correct answer is C.
upvoted 0 times
...
Nieves
6 months ago
No, because a separate closure stage plan should be created during stage 4.
upvoted 0 times
...
Laticia
6 months ago
I agree, closure activities should have been planned earlier.
upvoted 0 times
...
Marilynn
6 months ago
I think the correct answer is C.
upvoted 0 times
...
Magda
6 months ago
I think the correct answer is C.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77