Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 3 Question 67 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 67
Topic #: 3
[All PRINCE2-Practitioner Questions]

The project is in stage 3. Zero time tolerance has been given for this stage. When checking progress, the project manager noticed that the checkpoint report from the external supplier of the 'e-learning course' is late. As work package progress information is missing, the project manager has decided to raise an exception report.

Is this an appropriate action, and why?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Luann
4 months ago
Option C is a bit odd. Why would the project manager check the operations and maintenance interfaces first? That seems like a waste of time when the real issue is the late checkpoint report.
upvoted 0 times
Deonna
3 months ago
Option C is a bit odd. Why would the project manager check the operations and maintenance interfaces first? That seems like a waste of time when the real issue is the late checkpoint report.
upvoted 0 times
...
Sherita
3 months ago
B) Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
upvoted 0 times
...
Huey
3 months ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...
...
Loreta
4 months ago
Ha! The project manager is in a real pickle here. Raising an exception report is the way to go, but I bet they're wishing they had a time machine to turn back the clock and get that report on time.
upvoted 0 times
Salley
4 months ago
Ha! The project manager is in a real pickle here. Raising an exception report is the way to go, but I bet they're wishing they had a time machine to turn back the clock and get that report on time.
upvoted 0 times
...
Clorinda
4 months ago
B) Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
upvoted 0 times
...
Tiera
4 months ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...
...
Whitney
5 months ago
D) No, because the team plan should be discussed with the supplier to check whether work will be completed on time.
upvoted 0 times
...
Weldon
5 months ago
C) No, because the project manager should check the operations and maintenance interfaces in the work package first.
upvoted 0 times
...
Rebecka
5 months ago
I'm not so sure about that. I'd go with option D - the project manager should discuss the team plan with the supplier to see if the work will still be completed on time.
upvoted 0 times
Benton
3 months ago
Yes, but discussing the team plan with the supplier can help find a solution.
upvoted 0 times
...
Judy
3 months ago
But isn't it important to follow the zero time tolerance policy in this stage?
upvoted 0 times
...
Anglea
3 months ago
Option D is a good point. Communication with the supplier is key.
upvoted 0 times
...
Brice
3 months ago
Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
upvoted 0 times
...
Yolande
4 months ago
User Comment: I'm not so sure about that. I'd go with option D - the project manager should discuss the team plan with the supplier to see if the work will still be completed on time.
upvoted 0 times
...
Frank
4 months ago
Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...
...
Rosann
5 months ago
B) Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
upvoted 0 times
...
Kindra
5 months ago
I think B is the right answer. With zero time tolerance, the checkpoint report has to be delivered on time, no exceptions.
upvoted 0 times
Roselle
4 months ago
B) Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
upvoted 0 times
...
Jesusa
5 months ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...
...
Ciara
5 months ago
Definitely option A. The project manager needs to raise an exception report to get guidance on how to handle this situation with the late checkpoint report.
upvoted 0 times
Estrella
5 months ago
B) Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
upvoted 0 times
...
Joanna
5 months ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...
...
Malika
5 months ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77