PRINCE2 Exam PRINCE2-Practitioner Topic 3 Question 75 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 75
Topic #: 3
[All PRINCE2-Practitioner Questions]

During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered.

What should project assurance do next?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Johnetta
2 months ago
Haha, this is a classic project management question. I'd go with C, but B is also a valid option. 'Approved' is the magic word here.
upvoted 0 times
...
Antonio
2 months ago
This is a no-brainer. Option C is the correct answer. Approving the products is the key priority here.
upvoted 0 times
...
Theron
2 months ago
I think D is the right answer. Updating the stage plan to show the work package as completed is a logical next step.
upvoted 0 times
Allene
11 days ago
So, should we update the team plan to show that the work package is complete as well?
upvoted 0 times
...
Farrah
14 days ago
Yes, that's important too. We need to make sure everything is approved.
upvoted 0 times
...
Dorethea
1 months ago
But shouldn't we also check the work package and follow the procedure to deliver completed products?
upvoted 0 times
...
Dick
1 months ago
I agree, updating the stage plan makes sense.
upvoted 0 times
...
...
Suzan
2 months ago
B is the way to go. Checking the work package and following the procedure is the standard process to deliver completed products.
upvoted 0 times
...
Loren
2 months ago
Option C seems to be the most appropriate choice. Verifying that all the products to be delivered are approved is a crucial step to ensure the quality of the project.
upvoted 0 times
Tawanna
29 days ago
C) Verify that all the products to be delivered by the work package are approved.
upvoted 0 times
...
Lindsey
1 months ago
B) Check the work package and follow the procedure to deliver completed products.
upvoted 0 times
...
Maxima
1 months ago
A) Update the team plan to show that the work package is complete.
upvoted 0 times
...
...
Truman
2 months ago
But shouldn't project assurance also verify that all the products to be delivered are approved?
upvoted 0 times
...
Galen
3 months ago
I agree with Lynna. It's important to keep the team plan updated.
upvoted 0 times
...
Lynna
3 months ago
I think project assurance should update the team plan to show that the work package is complete.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77