PRINCE2 Exam PRINCE2-Practitioner Topic 3 Question 78 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 78
Topic #: 3
[All PRINCE2-Practitioner Questions]

The project is approaching the end of stage 4 and all work will be completed as planned. The project manager is now preparing a plan for acceptance and the handover of the 'capability to provide health and safety training'.

Is this appropriate, and why?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Lavonne
26 days ago
I'm going with C. Closure planning should have happened at the end of stage 3, not in the final stages of the project. Cutting it a bit close, aren't they?
upvoted 0 times
Oliva
4 days ago
Reta: That's possible. It's always better to plan ahead for these things.
upvoted 0 times
...
Rory
14 days ago
User 3: Maybe they underestimated the importance of planning for closure earlier in the project.
upvoted 0 times
...
Reta
16 days ago
User 2: I agree, it does seem a bit last minute to be planning for closure now.
upvoted 0 times
...
Sherill
17 days ago
User 1: I think C is the right choice. Closure planning should have been done earlier.
upvoted 0 times
...
...
Na
1 months ago
Haha, I bet the project manager is just trying to check one more box on their to-do list. Better late than never, I guess!
upvoted 0 times
Marleen
5 days ago
Dong: The project manager is probably just making sure everything is in order before closing out the project.
upvoted 0 times
...
Santos
9 days ago
User 3: I agree, a separate closure stage plan should be created during stage 4.
upvoted 0 times
...
Dong
23 days ago
User 2: Yes, a plan should be created to measure the number of courses carried out after project closure.
upvoted 0 times
...
Ashley
1 months ago
User 1: I think it's appropriate to prepare a plan for acceptance and handover at this stage.
upvoted 0 times
...
...
Rutha
2 months ago
I believe option B is the best choice, as a separate closure stage plan should be created during stage 4.
upvoted 0 times
...
Theron
2 months ago
I agree with Lorrie. Closure activities should have been planned earlier in the project lifecycle, not at the end of stage 4.
upvoted 0 times
...
Melodie
2 months ago
I agree with Iola. It's important to have a plan in place for a smooth transition.
upvoted 0 times
...
Lorrie
2 months ago
I think option D is the correct answer. User acceptance should be an ongoing process throughout the project, not just at the end.
upvoted 0 times
Derick
29 days ago
Eladia: Definitely, it helps ensure the project meets their needs.
upvoted 0 times
...
Alona
1 months ago
User 3: Yes, it's important to involve users throughout the project.
upvoted 0 times
...
Donette
1 months ago
User 3: Yes, it's important to involve users throughout the project.
upvoted 0 times
...
Eladia
1 months ago
User 2: I agree, user acceptance should be ongoing.
upvoted 0 times
...
Cassandra
1 months ago
User 1: I think option D is the correct answer.
upvoted 0 times
...
Tyra
1 months ago
I agree, user acceptance should be ongoing.
upvoted 0 times
...
Huey
1 months ago
I think option D is the correct answer.
upvoted 0 times
...
...
Iola
2 months ago
I think it's appropriate to prepare a plan for acceptance and handover.
upvoted 0 times
...