PRINCE2 Exam PRINCE2-Practitioner Topic 4 Question 60 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 60
Topic #: 4
[All PRINCE2-Practitioner Questions]

The project is approaching the end of stage 4 and all work will be completed as planned. The project manager is now preparing a plan for acceptance and the handover of the 'capability to provide health and safety training'.

Is this appropriate, and why?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Helene
6 months ago
I think measuring the number of courses after project closure is crucial for success.
upvoted 0 times
...
Lili
6 months ago
I believe user acceptance should have been ongoing throughout the project.
upvoted 0 times
...
Lorrine
7 months ago
I disagree with I think it's better to have a separate closure stage plan.
upvoted 0 times
...
Jeanice
7 months ago
I feel like closure activities should have been planned earlier in the project.
upvoted 0 times
...
Brice
7 months ago
I agree with having a plan in place is important for a smooth transition.
upvoted 0 times
...
Moira
7 months ago
I think it's appropriate to prepare a plan for acceptance and handover.
upvoted 0 times
...
Jin
8 months ago
Ah, come on Lyla, be fair. Maybe the project manager was new to the role and didn't know any better. We've all been there, right? Still, I agree that D is the right answer here.
upvoted 0 times
...
Lyla
8 months ago
Haha, the project manager must have been sleeping on the job if they waited until the end to plan for acceptance. What, did they think the client was just going to magically appear and say 'Looks good, ship it!'?
upvoted 0 times
...
Jeffrey
8 months ago
Hmm, I see what you're saying Ronnie, but I don't think that's a good enough reason. The project manager should have been proactive and got the client involved throughout the process, not just at the end.
upvoted 0 times
...
Ronnie
8 months ago
You guys make a good point. But what if the client wanted to wait until the end to do the acceptance? Wouldn't that be a valid reason to plan for it at the end of stage 4?
upvoted 0 times
...
Jesusa
8 months ago
I agree with Shannon. Waiting until the end of the project to plan for acceptance and handover is a bit late in my opinion. Shouldn't that have been part of the project plan from the beginning?
upvoted 0 times
...
Shannon
8 months ago
Hmm, this question seems pretty straightforward. I think the appropriate answer is D - user acceptance should have happened throughout the project, not just at the end.
upvoted 0 times
Vallie
7 months ago
I think closure activities could have been planned earlier.
upvoted 0 times
...
Brock
7 months ago
Yes, a plan should be created for that.
upvoted 0 times
...
Phillip
7 months ago
I agree, user acceptance should happen throughout.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77